Project: Ardfert Quarry Bridge
Client: Ardfert Quarry Products Ltd
Location: Ardfert, Co Kerry
Brief Overview:
The works involved the installation of 32m long precast concrete bridge beams and in-situ deck, pavement tie-ins to the existing local road running to the north of Ardfert Quarry.
The proposed cross section is a 4.2m carriageway, with 0.5m hard strips on each edge and precast concrete parapets screening public views into Ardfert Quarry.
Key Elements:
- Site set-up
- Site clearance and security
- Traffic management for construction of the bridge
- Fencing
- Protection of existing utilities / services and provision of new utility ducts
- Fabrication of precast elements
- Precast element transportation and erection
- End support construction including wingwalls
- Bridge deck construction
- Bridge finishes
- Embankment construction
- Backfilling and pavement construction
- Road construction and tie ins to the existing local road
- Construction of new road drainage (within Bridge Works contract)