Project: South East Greenway Contract A
Client: Wexford County Council
Location: New Ross to Waterford Railway Line
Brief Overview:
The works involved the construction of two separate lots (3km length) of the proposed 24km long, 5m wide greenway along the disused New Ross to Waterford rail corridor. The site location for Lot 1 starts at the southern end of Red Bridge and proceeds in the direction of Waterford for 1.2 km and the site location for Lot 2 starts at Abbey Road and proceeds in the direction of New Ross for 1.8 km.
Key Elements:
- Temporary traffic management
- Environmental management
- Health & Safety management
- Site clearance
- Fencing
- Earthworks
- Drainage & ducting
- Pavement works
- Kerbs, footways and paved areas
- Structural concrete
- Masonry
- Traffic signs and road markings
- Installation of public lighting